RBFCU/Bedford
$719,000
- Mark Engelke
- 210.300.9312
- 6,000 SF remodel of existing bank building
Well Fargo/Fossil Creek
$53,000
- Ed Adams
- 972-419-3127
- Haltom City, TX
ZYN22 REMODEL/Park Lane
$65,000
FW Country Day/Backstage Remodel
$97,000
- Clovis Murphree
- 817-312-9058
ZYN22 REMODEL/7th Street
$60,000
City Point UMC
$464,000
- Kyle Hantz
- 817-341-1588
- Renovated sanctuary with new concrete stage and communion rails
FW Plastic Surgery ’18
$112,500
- Dr. Polavarapu-Owner
- 773.710.6128
- 1,500 SF interior remodel with Exam & Procedural Rooms
Dallas Eye Care/Dallas ’17
$456,900
- Wendy Wilbanks-CFO
- 817.784.0222
- Complete 2nd Floor remodel, while in operation, 8200 SF
Biomat Lobby Remodel ’17
$105,600
- Leonor Vincente, Facility Manager
- 817-570-9212
- Lobby remodel and business remained in operation-2 phases
Southwest Bank/Luna ‘16
$423,000
- Evelyn Dedman, Facilities Mgr.
- 817-298-5655
- 4,600 SF interior remodel while bank remained in operation-2 phases
-
Evangelista Eye Care/Arlington ’17
$223,300
- Wendy Wilbanks-CFO
- 817.784.0222
- Exterior and interior remodel with ADA updates
Gatehouse/Commercia ‘16
$2,035,900
- Bob James, Facilities Mgr.
- 817-253-6299
- 12,000 SF strip-center shell, steel structure
Christ Chapel/West Campus ’16
$1,849,000
- Rick Neves, COO 817-731-4329
- Renovation of 2 existing structures, with various sport facilities between
Wells Fargo/Conversions ’10
$3,150,000
- Dave Clark-Facility Mgr.
- 817-676-4281
- Interior/exterior remodel, 31 Wacovia Branches, 4000 SF each
First Financial Bank/Southlake '12
$1,650,000
- Mark Jones
- 817.410.2928
- New Construction of 6,500 SF branch bank, wood structure, with 4-lane drive in facility
Woodhaven Bank/Colleyville ‘09
$449,000
- Sharon Burran-Pres/COO
- 817-496-6700
- 4,200 SF interior/exterior renovation
EECU/Saginaw ‘08
$1,175,300
- Cindy Baker-COO
- 817-882-0100
- 4,700 SF branch bank, wood/steel structure, finished in 110 days.
Christ United Methodist Church ‘08
$640,000
- Don Painter-Elder
- 817-386-2938
- 6,000 SF wood/steel structure addition
EECU/28th Street ‘07
$1,637,000
- Cindy Baker-COO
- 817-882-0100
- 15,000 SF concrete tilt-up building, with 4,000 SF branch bank
Wells Fargo/Heritage ’07
$1,295,000
- Guy Holbert-Project Mgr.
- 817-501-5082
- 5,700 SF-wood structure, built/finished 109 calendar days
Magnolia Green CFA ‘06
$1,525,000
- Red Oak Realty (Jim Eagle)
- 817-877-3300
- Site modifications for new development, site utilities, sidewalks, park, streets
Surgical Associates/Grapevine ’14
$572,000
- Evelyn Dedman-SW/Bank
- 817-298-5655
- 6,000 SF interior medical finish out with Exam/Procedural Rooms
Texas Cancer Care Vault ‘06
$252,000
- Cindy Glickman-Proj.Mgr.
- 817-333-0144
- Concrete vault for gamma-ray MRI
Wells Fargo/Denton-Brinker ‘06
$1,650,000
- David Frederick-Proj.Mgr.
- 817-789-2241
- 6,000 SF-wood structure, built/finished 78 working days
Wells Fargo/Grand Prairie‘06
$212,000
- Guy Holbert
- 817-501-5082
- Interior Construction
Wells Fargo/Denton-University ‘06
$1,650,000
- David Frederick-Proj.Mgr.
- 817-789-2241
- 6,000 SF-wood structure, built/finished 78 working days
Metro Liquor Store ’05
$678,000
- Picash Petel-Owner
- 817-296-9910
- 6,000 SF-CMU/steel joists/B.U.roof, completed 6 months
Lancaster Lofts/Ft. Worth-’04
$940,000
- Flora Brewer
- 817-335-2561
- 15,000 SF-1934, 4-story building converted into lofts-4 months
Southwest Vision Center/NRH ’97
$350,000
- 5,000 SF-wood structure, with 4 examination rooms, brick/E.I.F.S. skin-6 months
Ironhorse Clubhouse-'90
$750,000
- City of NRH (Richard Davis)
- 817-832-2686
- 6,800 SF-Wood Frame-6 months
Christ Chapel Phases I-III ‘99
$683,000
- Bill Egner-Exec.Pastor
- 817-731-4329
- Single Story Structure and Interior Construction
- 5,700 SF-wood structure, built/finished 90 calendar days
Comerica Bank/Irving-'91
$210,000
- Comerica (Adena Nichols)
- 214-589-2922
- 4 lane drive-in facility, steel structure, plaster skin-3 months
- v